Guides01 Site
Before you make an offer: four checks on an Auckland development site
Problems cost least on paper, before you own the land. How to screen a site with a simple funnel, and the four checks to do before you make an offer.
The most expensive mistake in development isn’t a project that fails its numbers. It’s a project that passes its numbers on an assumption nobody checked.
Say you buy a site believing four homes can connect to the wastewater pipe in the street. You pay for a design around that belief, and you apply for consent around it. Then the engineer finds the pipe is too shallow, or has no spare capacity. Everything you’ve spent so far rests on something nobody checked. Asked before the offer, the same question might have cost a phone call and a few hundred dollars of someone’s time.
Problems cost more the later you find them
- Before the offer, a problem is a note on paper.
- After you buy, you own it.
- After consent, your design and your consent are built around it.
- During the build, it can cost the project.
So the cheapest place to find a problem is right at the start, before you make an offer.
Think of a funnel
We think of screening sites as a funnel. At the wide top, you look at lots of sites, quickly and cheaply. Each time a site survives a stage, you spend a little more to answer the next question. Only a few sites reach the bottom, where you make a real commitment.
- A first conversation
- The servicing question: can the site connect to water, wastewater and stormwater?
- Records and screening
- A coordinated investigation, with your consultants working from the same information
- The decision to commit
The rule is simple: spend in proportion to the decision in front of you. Don’t pay for a full design to find out whether a pipe is deep enough.
Most sites are meant to fall out of the funnel. When you read a site’s information and walk away, often having spent nothing, that isn’t failure. It’s the funnel doing its job. Every site you drop early is a mistake you didn’t make.
Start with a first filter
Send a designer enough to identify the site and what you’d like to build there. Mention anything unusual, like a corner site, a slope or a house you’d keep. Ask what the likely constraints are, and what they’d need to know next. Agree up front whether that first conversation is charged, and where paid work starts.
The answer will almost always come with a condition: “This may work, if the wastewater can be connected.” That’s useful, but it’s a question to hand to someone, not a green light. Write it down, and decide who will answer it.
The four checks
Next, put together a four-part screen for the site: one site, one dated pack. Each check answers a different question and comes from a different source.
1. The services map
Where do the water, wastewater and stormwater pipes appear to run? Auckland Council’s GeoMaps viewer shows mapped underground services. But a pipe on a map near your boundary doesn’t prove you can connect to it. That’s a question for an engineer.
2. Hazard information
Flooding, overland flow paths, and any ground that may be unstable. GeoMaps includes Council’s flood modelling, which Council describes as indicative. Save what you see with the date you looked. A blank map isn’t proof there’s no risk.
3. The title, and what’s registered on it
Easements, covenants and consent notices can limit what you build and where. You can order the current record of title from Toitū Te Whenua Land Information New Zealand (LINZ). Read the registered documents themselves with your lawyer, not just the one-line summaries on the front page.
4. A planner’s written check
Which zone and rules apply to what you actually want to build, and what could change that advice. Rules do change: Auckland’s housing rules are being reviewed through Plan Change 120, and Council expects to make its decisions around mid-2027. Ask your planner to put the answer in writing, with the date.
Keep each check with its date and where it came from.
Agent packs and LIMs
When you ask about a site, the agent will often send you a pack: a LIM, the title, sometimes a plan. A LIM, or Land Information Memorandum, is Council’s summary of certain information it holds about a property, as at the date it’s issued. It isn’t a site inspection. If something isn’t recorded, that doesn’t mean it isn’t there.
Read the pack. It’s good for three things: ruling a site out fast, shortlisting it, or briefing your designer. But read the disclaimer too, because the agent isn’t standing behind it. If a site survives to an offer, get your own current records, and ask your lawyer what you need in your own name.
Ask three people the same question
Once the pack is together, ask your designer, a civil engineer and a planner the same open question: “What can this site reasonably support, what could stop it, and what should we check next?”
Then put their answers side by side. The designer may fit a layout the engineer can’t service. The planner may flag an access problem that changes both. Better to find those clashes now than after you’ve paid for detailed drawings.
James’s first site
James is a made-up example.
James’s designer says four homes “may be worth testing, provided access and servicing work”. James’s first instinct is to reply, “Great, please start the design.” That would spend real money before anyone has checked the two things the designer flagged.
So James works through the top of the funnel instead. He saves the services and flooding maps, with the date. He orders the title. He asks a planner and a civil engineer the same question the designer answered. And he writes down, in one place, what he’s hoping for and what has actually been checked.
Try it now
Pick a site you own or are watching. Open Auckland Council GeoMaps, turn on the underground services and flooding information, and save both with today’s date. That’s two of the four checks started. Then note what you’d still need for the other two: the title, and a planner’s written check.
Problems are cheapest on paper, before the offer. Spend in proportion to the decision in front of you, and treat walking away early as the funnel working, not failing.
Sources
- GeoMaps mapping service Auckland Council, checked 27 October 2026
- PC 120 info sheet 23: flood hazard information in GeoMaps Auckland Council, checked 27 October 2026
- Record of title (current) Toitū Te Whenua Land Information New Zealand, checked 27 October 2026
- How to order a Land Information Memorandum (LIM) Auckland Council, checked 27 October 2026
- PC 120 Independent Hearings Panel Auckland Council, checked 27 October 2026